Risk & Issue Register

Search, filter, and manage all recorded risks and issues.

TypeStatusPriorityOwnerDue DateProbabilityImpact
Provision of Surety letter
Redundant Rockwell PLC with 1200 Hardwired I/O and 21 third party packages
Woodrow Dinstel
17/03/202590%0.80
Communication on RS 485
Tank Farm Booster Pumps Controller Upgrade
Imran Ahmed
15/11/202550%0.40
Harsh Rainy Weather at Site
EPWD Offshore ICS SOWIP Tie-In Project
Asif Zafar
01/06/202570%0.20
Material PO is not received yet
Supply and Services of Server Machine
Umer Ilyas
15/05/202590%0.20
Lack of Clarity in the Actual Situation of the Project
Power Supply skid automation for Electrical submersible Pump Application - ADNOC
Usman Dodhy
31/01/202550%0.20
Imposition of new tariffs
6 RTU Buildings
Woodrow Dinstel
20/06/202590%0.80
Change in site execution scopes due to managment change
F&G and ESD Systems Upgrade at Imo AGG
Olaoluwa Adebayo
01/04/202550%0.20
Commissioning the Remaining Loops
IPF Phase 2 DED
Ahmed Mohamed Esmail
16/01/202690%0.80
Delay in delivery of material for Solar System & Telecom
Buoy PLC and Telemetry Control System Upgrade
Imran Ahmed
15/07/202550%0.80
Changes in Control Philosophy
Graphics to Match JBDV - EPCOR Contract
Andres Paris
08/04/202450%0.40